Proposition #5

Zoo Improvements

$1,030,000

All design activities for the five Abilene Zoo bond projects were completed during Phase 1. The Phase 2 construction activities will be combined into one bid to save time and money, and all will begin in 2017.

  • A new exhibit of African lesser flamingos, which will greet visitors as they enter the Zoo
  • Jaguar facility renovation and expansion, adding off-exhibit space for breeding and rearing these endangered cats
  • A new bird rehabilitation facility with much-needed room for the zoo’s efforts to protect our region’s native species
  • A new giant anteater exhibit
  • Renovations to the fishing pier to provide access for guests with disabilities

Project Status

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-design Fall 2016 Design complete, construction to begin in 2017  2017 
    BondGraphics-design Spring 2016  Design for this facility is currently underway with the local firm of Parkhill, Smith &
    Cooper.
  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-construction
     Spring 2017 Construction begins 
    BondGraphics-design  Spring 2016 Design complete, construction to begin in 2017 
    2017
    BondGraphics-design  Fall 2015 Design phase begins   

    November 2017 Updates

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-design
     Fall 2016 Design complete, construction to begin in 2017 
     2017
    BondGraphics-design  Spring 2016 Design for this facility is currently underway with the local firm of Parkhill, Smith &
    Cooper.



  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-design Fall 2017 Design complete, construction to begin in 2017 2017

    November 2017 Updates

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-design 2017 Design complete, construction to begin in 2017 2017




 Spring 2016 Design has been completed for this facility
2017