BondGraphics-1Streets
Proposition #1

Streets

$45,975,000

The Streets & Road Improvements project will work on approximately 130 lane miles of roadway to rehabilitate existing travel lanes, replace and upgrade drainage facilities and curb and gutter, reconstruct intersections, create new travel lanes, reconstruct existing driveways and sidewalks where needed, and upgrading signal infrastructure with improved technology.

Phase 1 Projects included Judge Ely Boulevard, West Lake Road, Antilley Road, Catclaw Drive, and the beginning of utility improvements for Ambler Avenue.

Phase 2 Projects, beginning in spring of 2017, are the continuing of Ambler Avenue and work beginning on Hardwick Road, North Third Street, South 20th Street, Texas Avenue, the Central Business District (CBD), South of Downtown Abilene (SoDA), and various traffic signal improvements.

 

Completed Projects

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-completed
    August, 2016  Construction complete!   
    BondGraphics-construction 4/6/16  Construction begins  June 2016
    1/12/16   Bid awarded
    BondGraphics-design  3/28/16 Design phase ends

    BondGraphics-design  Fall 2015 Design phase begins   

    Antilley Road from Buffalo Gap Road to Directors Parkway was repaved, and bicycle signs were added. Construction was completed in August 2016.

    May 2016 Updates

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-completed
    Aug 24, 2016  Construction complete!  
    BondGraphics-construction
    May 2, 2016 Construction begins  Sept 2016
    Feb 9, 2016  Bid awarded 
    BondGraphics-design Feb 2016 Design Phase ends


    Judge Ely Boulevard was reconstructed from East Highway 80 to East North 16th Street, and repaved from East North 16th to Ambler Avenue. Construction was completed in August 2016, ahead of schedule and under budget.

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-completed
    Aug 28, 2016  Construction complete!  
    BondGraphics-construction Mar 29, 2016 Construction begins Aug 2016
    BondGraphics-design March 2016   Design phase ends
    Construction scheduled to begin 3/28/16
     
    BondGraphics-bidawarded Jan 26, 2016 Bid awarded  

    West Lake Road from Ambler Avenue to Anson Avenue was widened and reconstructed, with paved shoulders and culvert improvements. Construction was completed in August 2016, ahead of schedule and under budget.

    WestLake-forweb

    WestLake-forweb2

    May 2016

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-completed
    Oct 17, 2016 Construction complete!  
    BondGraphics-construction May 2, 2016  Construction begins Oct 2016
    BondGraphics-design March 28, 2016 Design phase ends

    BondGraphics-bidawarded  Feb 23, 2016  Bid awarded  
    BondGraphics-design Fall 2015  Design phase begins 

    Catclaw Drive from Rebecca Lane to Curry Lane was reconstructed, adding curbs and gutters. Construction was completed in October 2016.

    Catclaw-forweb

    Catclaw-forweb2
  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-completed April 6, 2017  Construction complete!
    BondGraphics-construction Spring 2017 Construction begins Spring 2017  

    Dub Wright to Hwy 277 S.
  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-completed
    May 31, 2017 Construction complete - Grand Opening!  
    BondGraphics-construction
     April 2017 CBD Hot Mix construction begins Summer 2017
    BondGraphics-design
     Spring 2017 CBD Hot Mix design complete
    CBD Concrete design underway 
     
    BondGraphics-design Spring 2016 The Design Contract for the project has been awarded to the local firm enprotech/Hibbs & Todd. The project is currently under design


  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-completed
    June 7, 2017  Construction complete - Ribbon Cutting Grand Opening!  
    BondGraphics-construction
     April 2017 Construction begins  Summer 2017
    BondGraphics-design  Spring 2017 Design complete

    Sayles Blvd. to Treadaway Blvd.

Project Status

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-construction
    May 9, 2017 Road Construction begins Fall 2017
    BondGraphics-construction
    Aug 30, 2016  Utility improvement projects under roadway begin 
    BondGraphics-design   Design complete   
    BondGraphics-upcoming 2016 Planning Improvements, scheduled to begin in 2017

    Phase 1 - Ambler Avenue utility improvements began construction in August 2016. This project, funded by Water Utility Department cash reserves, is replacing the underground water and sewer lines before work on the roadway can begin.

    Phase 2 - After the Ambler Avenue utility improvements are complete in spring 2017, the street will be repaved from Danville Drive to Treadaway Boulevard.

    January 2017 Updates

  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-design  Spring 2016 A Design Contract has been awarded to Iteris, Inc. This contract is to design all of the traffic signals and controls for all of the 2015 Bond Street projects. The design team is currently working with City Staff to design traffic signal improvements.  TBD


  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-design  Spring 2017 Design complete, construction to begin soon TBD

    Beltway S. to Antilley Rd.
  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-construction
    April 2017  Construction begins   TBD
    BondGraphics-design Spring 2017 Design complete

    Willis St. to Hickory St.
  • STATUS DATE  DETAILS TARGET COMPLETION
    BondGraphics-design
     Spring 2017 Design complete, construction to begin May 2017  TBD
    BondGraphics-design Spring 2016 The Design Contract for this project has been awarded to the local firm Jacob & Martin. The project is currently under design.


Improvements Scheduled after 2017:

  • Industrial Blvd. (Treadaway Blvd. to Maple St.)
  • N. Willis St. (N. 1st St. to Vogel Ave.)
  • Old Anson Rd. (Ambler Ave. to W. Stamford St.)
  • Pioneer Dr. (S 14th St. to S. 7th St.)
  • Corsicana Ave. (Texas Ave. to Benbrook St.)
  • Hartford St. (Veterans Blvd. to Clack St.)
  • Leggett Dr. (S. 7th St. to S. 1st St.)
  • N. 1st St. (RR tracks west of Wall St. to Pioneer Dr.)
  • Vogel St. (Danville Dr. to Grape St.)
  • Butternut St. (Treadaway Blvd. to S. 1st St.)
  • N. 6th St/Legget Dr. (N. 1st St. to Grape St.)
  • S. Willis St. (S. 32nd St. to S. 14th St.)
  • T&P Ln. (E.S. 11st St. to Sandy St.)